Granite Mountain
NEVADA, USA
Granite Mountain
Project Description
- 4 Leases – 12,273 Acres
- Reservoir Depth: 1000 – 1500m
- Expected Temperature: 150-200°C, 300-400°F
- Expected Flow: ≥ 360 m3/hour per production well
- Power Capacity: 30 MW (25 net)
- Yearly Production: 228 GWh
- COD 2030
The Granite Mountain project, located in Pershing County, was acquired by TLS in 2023 after DIG4GEO predicted a high geothermal favorability at this location. The project includes four geothermal leases on federal lands. No surface manifestations are present and no previous exploration has been done in this area.
TLS started exploration surveys, including geology, geophysics and geochemistry in early 2024. Data are currently being analyzed to confirm the geothermal potential of the area. Drilling targets for exploration drillings will be defined to start the permitting process in late 2025.